SR Toombs
250 MW generation in Toombs, GA · In queue since April 2020 · Proposed COD November 2024
250 MW
Capacity
1
Components
Solar
6y 1m
In Queue
Construction
IA Status
COD target: 2024
Total Duration
4y 7m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-30
The SR Toombs project is a proposed 250 MW solar generation facility located in Toombs County, Georgia. The project is in the Georgia Transmission (GTC) interconnection queue (GTC-GI-139), with an initial queue entry date of April 17, 2020. The proposed commercial operation date is November 30, 2024, and the project's interconnection agreement status is currently listed as "Construction".
The project, which appeared in recent news coverage, consists of 250 MW of solar photovoltaic generation. The point of interconnection is the Wadley Primary - Vidalia 230 kV substation.
Generated from interconnection queue and public data sources
State
GA
County
Toombs
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Wadley Primary - Vidalia 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about SR Toombs