Cherry Blossom Solar
150 MW hybrid in Twiggs, GA · In queue since August 2020 · Proposed COD June 2023
150 MW
Capacity
1
Components
Solar
5y 9m
In Queue
Facility Study
IA Status
COD target: 2023
Total Duration
2y 10m
Schedule
35 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-15
Cherry Blossom Solar is a proposed 150 MW hybrid solar and battery energy storage project located in Twiggs County, Georgia. The project is listed in the Georgia Transmission (GTC) interconnection queue as queue ID GTC-GI-142, with an entry date of August 13, 2020. The proposed commercial operation date is June 15, 2023, and the project's interconnection agreement status is currently in the Facility Study phase.
The development project consists of 150 MW of solar photovoltaic generation. Cherry Blossom Solar has been mentioned in recent news coverage related to development activities.
Generated from interconnection queue and public data sources
State
GA
County
Twiggs
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Danville 115 kV Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN