Dellwood Solar
150 MW hybrid in Emanuel, GA · In queue since May 2021 · Proposed COD February 2024
150 MW
Capacity
1
Components
Solar
5 years
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
2y 9m
Schedule
27 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-28
The Dellwood Solar project is a proposed 150 MW hybrid solar and battery energy storage project located in Emanuel County, Georgia. Interconnecting to the Georgia Transmission (GTC) grid at the Vidalia-Wadley Primary (white) 230 kV line, the project entered the GTC interconnection queue (GTC-GI-149) on May 4, 2021. The proposed commercial operation date is February 28, 2024, and the project's interconnection status is currently in the Facility Study phase.
The development project consists of 150 MW of solar photovoltaic generation capacity. It is listed as an active project in the interconnection queue. The developer is not specified in the available data, but the project has appeared in recent news coverage regarding renewable energy development in the Southeast region.
Generated from interconnection queue and public data sources
State
GA
County
Emanuel
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Vidalia-Wadley Primary (white) 230 kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.