SR DeSoto II
65 MW hybrid in Lee, GA · In queue since June 2021 · Proposed COD November 2023
65 MW
Capacity
1
Components
Solar
4y 11m
In Queue
Operational
IA Status
COD target: 2023
Total Duration
2y 5m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-30
The SR DeSoto II project is a proposed 65 MW solar and battery hybrid development in Lee County, Georgia. Interconnecting to the Georgia Transmission (GTC) system, the project entered the GTC queue (GTC-GI-151) on June 16, 2021, with a proposed commercial operation date of November 30, 2023. The interconnection agreement (IA) status is listed as Operational.
The project consists of 65 MW of solar generation capacity. It is located in the Southeast region and is actively listed in the interconnection queue. The point of interconnection (POI) is the N. Americus - N. Tifton 230 kV TL.
Generated from interconnection queue and public data sources
State
GA
County
Lee
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
N. Americus - N. Tifton 230 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about SR DeSoto II