Long Cane Solar
80 MW hybrid in Troup, GA · In queue since July 2021 · Proposed COD November 2024
80 MW
Capacity
1
Components
Solar
4y 10m
In Queue
System Impact Study
IA Status
COD target: 2024
Total Duration
3y 4m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-30
Long Cane Solar is a proposed 80 MW hybrid solar and battery energy storage project located in Troup County, Georgia. The project, under development by GTC, consists of 80 MW of solar generation capacity. It is interconnected to the Georgia Transmission Corporation (GTC) grid at the Glassbridge Tap 115 kV TL point of interconnection.
The project is listed in the GTC interconnection queue as project GTC-GI-153, with an entry date of July 19, 2021. Its proposed commercial operation date is November 30, 2024. The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
GA
County
Troup
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Glassbridge - Glassbridge Tap 115 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Long Cane Solar