Talbot Solar (GTC-GI-157) — Project Summary

Queue ID
GTC-GI-157
Capacity
150 MW
Technology
Solar
Status
active
Location
Talbot, GA
Region
Southeast
Developer
IA Status
Facility Study

Talbot Solar

GTC-GI-157BetaActiveSolarGTCLBNL

150 MW generation in Talbot, GA · In queue since December 2021 · Proposed COD December 2023

150 MW

Capacity

1

Components

Solar

4y 5m

In Queue

Facility Study

IA Status

COD target: 2023

Status
as of 2y 3m ago
Project statusUnder constructionGeorgia Public Broadcasting · 2024-02-20
Interconnection

Total Duration

2 years

Schedule

29 months past proposed COD

Facilities Study50%
Queue EntryDec 1, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-30

About

The Talbot Solar project is a proposed 150 MW solar generation facility in Talbot County, Georgia. The project is listed in the Georgia Transmission (GTC) interconnection queue as entry GTC-GI-157, with a queue entry date of December 1, 2021. The proposed commercial operation date is December 30, 2023. Its interconnection status is currently in the Facility Study phase.

The Talbot Solar project has been the subject of recent news coverage, with eight articles appearing in the press. These articles primarily focus on grid-related topics, with additional coverage of industry and development aspects of the project.

Generated from interconnection queue and public data sources

Project Details

State

GA

County

Talbot

Grid Region

Southeast

Market

Developer

Utility

Georgia Transmission

Entity

GTC

Service Type

Point of Interconnection

Talbot County Energy _x0013_ Butler Sub

Data Source

LBNL

CompanyTalbot CountyThe Star Democrat · 2021-03-02
Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Southern Company
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (2)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Talbot Solar