Talbot Solar
150 MW generation in Talbot, GA · In queue since December 2021 · Proposed COD December 2023
150 MW
Capacity
1
Components
Solar
4y 5m
In Queue
Facility Study
IA Status
COD target: 2023
Total Duration
2 years
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-30
The Talbot Solar project is a proposed 150 MW solar generation facility in Talbot County, Georgia. The project is listed in the Georgia Transmission (GTC) interconnection queue as entry GTC-GI-157, with a queue entry date of December 1, 2021. The proposed commercial operation date is December 30, 2023. Its interconnection status is currently in the Facility Study phase.
The Talbot Solar project has been the subject of recent news coverage, with eight articles appearing in the press. These articles primarily focus on grid-related topics, with additional coverage of industry and development aspects of the project.
Generated from interconnection queue and public data sources
State
GA
County
Talbot
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Talbot County Energy _x0013_ Butler Sub
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26