SR Rochelle Solar
120 MW generation in Wilcox, GA · In queue since December 2021 · Proposed COD November 2026
120 MW
Capacity
1
Components
Solar
4y 5m
In Queue
Construction
IA Status
COD target: 2026
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-11-01
The SR Rochelle Solar project is a proposed 120 MW solar generation project located in Wilcox County, Georgia. The project is listed in the Georgia Transmission Corporation (GTC) interconnection queue as entry GTC-GI-158, with a queue entry date of December 9, 2021. The proposed commercial operation date is November 1, 2026, and the project's interconnection agreement status is currently listed as "Construction".
The project connects to the Fitzgerald - Pitts 115 kV transmission line. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
GA
County
Wilcox
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Fitzgerald - Pitts 115 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about SR Rochelle Solar