Cherry Tree Solar
150 MW hybrid in Washington, GA · In queue since December 2021 · Proposed COD December 2025
150 MW
Capacity
1
Components
Solar
4y 5m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
4 years
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
Cherry Tree Solar is a proposed 150 MW hybrid solar and battery energy storage project located in Washington County, Georgia. The development project consists of 150 MW of solar photovoltaic generation. It is listed in the Georgia Transmission Corporation (GTC) interconnection queue as project GTC-GI-159, with a queue entry date of December 16, 2021, and a proposed commercial operation date of December 1, 2025. The project's interconnection point is the Sandersville-Wadley 230 kV line, and its interconnection status is currently in the Facility Study phase.
The Cherry Tree Solar project has appeared in recent news coverage regarding renewable energy development in the Southeast region.
Generated from interconnection queue and public data sources
State
GA
County
Washington
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Sandersville-Wadley 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Cherry Tree Solar