Meriwether Panther Solar
125 MW hybrid in Meriwether, GA · In queue since January 2022 · Proposed COD December 2026
125 MW
Capacity
1
Components
Solar
4y 4m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
The Meriwether Panther Solar project is a proposed 125 MW hybrid solar and battery energy storage project located in Meriwether County, Georgia. The project, which consists of 125 MW of solar generation, is in the Georgia Transmission Corporation (GTC) interconnection queue (GTC-GI-161). The queue entry date is January 28, 2022, and the proposed commercial operation date is December 31, 2026.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the GTC 115 kV substation on Rocky Mount Rd. The developer is not specified in the available data, but the project is within the service area of Georgia Transmission Corporation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
GA
County
Meriwether
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
GTC 115 kV substation on Rocky Mount Rd
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Meriwether Panther Solar