Two Rivers Solar (GTC-GI-162) — Project Summary

Queue ID
GTC-GI-162
Capacity
102 MW
Technology
Solar+Battery
Status
active
Location
Camden, GA
Region
Southeast
Developer
IA Status
Facility Study

Two Rivers Solar

GTC-GI-162BetaActiveSolarBatteryGTCLBNL

102 MW hybrid in Camden, GA · In queue since March 2022 · Proposed COD December 2024

102 MW

Capacity

1

Components

Solar

4y 2m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection

Total Duration

2y 9m

Schedule

17 months past proposed COD

Facilities Study50%
Queue EntryMar 16, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-20

About

Two Rivers Solar is a proposed 102 MW hybrid solar and battery energy storage project in Camden County, Georgia. The project consists of 102 MW of solar generation. It is located in the service territory of Georgia Transmission (GTC) and is listed in the GTC interconnection queue as queue ID GTC-GI-162. The project entered the queue on March 16, 2022, with a proposed commercial operation date of December 20, 2024. Its interconnection agreement status is currently in the Facility Study phase.

The Two Rivers Solar project has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

GA

County

Camden

Grid Region

Southeast

Market

Developer

Utility

Georgia Transmission

Entity

GTC

Service Type

Point of Interconnection

Browntown 115 kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Southern Company
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.