Little Cedar Solar
150 MW generation in Baldwin, GA · In queue since June 2022 · Proposed COD October 2025
150 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
3y 4m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-01
The Little Cedar Solar project is a proposed 150 MW solar generation facility located in Baldwin County, Georgia. The project is being developed within the Georgia Transmission Corporation (GTC) service area. It entered the GTC interconnection queue (GTC-GI-165) on June 20, 2022, with a proposed commercial operation date of October 1, 2025.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the North Milledgeville to Tap 230 kV transmission line.
Generated from interconnection queue and public data sources
State
GA
County
Baldwin
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
N. Milledgeville to Tap 230 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Little Cedar Solar