200 MW generation in Glynn, GA · In queue since June 2022 · Proposed COD August 2024
200 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
2y 2m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-08-30
Pepper Hammock Solar is a proposed 200 MW solar generation project located in Glynn County, Georgia. The project is listed in the Georgia Transmission (GTC) interconnection queue as queue ID GTC-GI-166, with an entry date of June 21, 2022. The proposed commercial operation date is August 30, 2024.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is the Offerman 230 kV -Thalmann 230 kV TL transmission line. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
GA
County
Glynn
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Offerman 230 kV -Thalmann 230 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.