Pepper Hammock 500 Solar (GTC-GI-168) — Project Summary

Queue ID
GTC-GI-168
Capacity
500 MW
Technology
Solar
Status
active
Location
Glynn, GA
Region
Southeast
Developer
IA Status
Facility Study

Pepper Hammock 500 Solar

GTC-GI-168BetaActiveSolarGTCLBNL

500 MW generation in Glynn, GA · In queue since July 2022 · Proposed COD August 2024

500 MW

Capacity

1

Components

Solar

3y 10m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection

Total Duration

2y 1m

Schedule

20 months past proposed COD

Facilities Study50%
Queue EntryJul 6, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-08-30

About

The Pepper Hammock 500 Solar project is a proposed 500 MW solar generation facility located in Glynn County, Georgia. The project is in the Georgia Transmission (GTC) interconnection queue (GTC-GI-168) as of July 6, 2022, with a proposed commercial operation date of August 30, 2024. Its interconnection status is currently in the Facility Study phase.

The project, which appeared in recent news coverage, consists of 500 MW of solar photovoltaic generation. The point of interconnection is the Hatch - Thalmann 500 kV transmission line.

Generated from interconnection queue and public data sources

Project Details

State

GA

County

Glynn

Grid Region

Southeast

Market

Developer

Utility

Georgia Transmission

Entity

GTC

Service Type

Point of Interconnection

Hatch - Thalmann 500 kV TL

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Southern Company
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.