Pepper Hammock 500 Solar
500 MW generation in Glynn, GA · In queue since July 2022 · Proposed COD August 2024
500 MW
Capacity
1
Components
Solar
3y 10m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
2y 1m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-08-30
The Pepper Hammock 500 Solar project is a proposed 500 MW solar generation facility located in Glynn County, Georgia. The project is in the Georgia Transmission (GTC) interconnection queue (GTC-GI-168) as of July 6, 2022, with a proposed commercial operation date of August 30, 2024. Its interconnection status is currently in the Facility Study phase.
The project, which appeared in recent news coverage, consists of 500 MW of solar photovoltaic generation. The point of interconnection is the Hatch - Thalmann 500 kV transmission line.
Generated from interconnection queue and public data sources
State
GA
County
Glynn
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Hatch - Thalmann 500 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.