Brenneman Solar
150 MW generation in Macon, GA · In queue since November 2022 · Proposed COD November 2024
150 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
2 years
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-30
The Brenneman Solar project is a proposed 150 MW solar generation facility located in Macon County, Georgia. Interconnection is being managed through the Georgia Transmission (GTC) queue, identified as GTC-GI-169, with an entry date of November 29, 2022. The proposed commercial operation date is November 30, 2024. The project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Brenneman Solar Project operating plant (EIA ID 66744). Recent news coverage indicates activity related to deals involving the Brenneman Solar project.
Generated from interconnection queue and public data sources
State
GA
County
Macon
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
North Americus _x0013_ Perry 115 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14