Ocilla Solar
150 MW generation in Irwin, GA · In queue since November 2022 · Proposed COD November 2025
150 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
3 years
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-30
The Ocilla Solar project is a proposed 150 MW solar generation facility located in Irwin County, Georgia. The project is in the Georgia Transmission Corporation (GTC) interconnection queue as project GTC-GI-170, with a queue entry date of November 30, 2022. The proposed commercial operation date is November 30, 2025.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Lake Beatrice - Stump Lake 115 kV transmission line.
Generated from interconnection queue and public data sources
State
GA
County
Irwin
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Lake Beatrice - Stump Lake 115 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Ocilla Solar