Southern Sky Solar
102 MW hybrid in Clinch, GA · In queue since March 2023 · Proposed COD September 2026
102 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
Southern Sky Solar is a proposed solar and battery hybrid project with a total capacity of 102 MW located in Clinch County, Georgia. The project is in the Georgia Transmission (GTC) interconnection queue, identified as GTC-GI-171, with a queue entry date of March 17, 2023. The proposed commercial operation date is September 30, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The development project consists of 102 MW of solar capacity. The point of interconnection is the Tarver - West Homerville 115 kV TL. The Southern Sky Solar project has been mentioned in recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
GA
County
Clinch
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Tarver - West Homerville 115 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.