Red Dirt Solar
153 MW hybrid in Talbot, GA · In queue since April 2023 · Proposed COD September 2026
153 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
Red Dirt Solar is a proposed 153 MW hybrid solar and battery energy storage project located in Talbot County, Georgia. The development project consists of 153 MW of solar photovoltaic generation. It is interconnected to the Georgia Transmission Corporation (GTC) system and is listed in the GTC interconnection queue as project GTC-GI-172. The project entered the queue on April 6, 2023, with a proposed commercial operation date of September 30, 2026. Its interconnection agreement status is currently in the Facility Study phase.
The Red Dirt Solar project has been the subject of recent news coverage, with four articles published related to the industry and regulatory aspects of the project.
Generated from interconnection queue and public data sources
State
GA
County
Talbot
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Patsiliga Creek - Talbot County #1 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Red Dirt Solar