SR Norwood Solar
107 MW generation in Warren, GA · In queue since May 2023 · Proposed COD June 2026
107 MW
Capacity
1
Components
Solar
3 years
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-30
The SR Norwood Solar project is a proposed 107 MW solar generation facility located in Warren County, Georgia. The project is interconnected to the Georgia Transmission Corporation (GTC) system and entered the GTC interconnection queue (GTC-GI-173) on May 2, 2023. Its proposed commercial operation date is June 30, 2026, and its interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing SR Norwood operating plant (EIA plant ID 68563). The project has also appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
GA
County
Warren
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Ray Place Road-Warrenton Primary 115 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.