Live Oak Solar
200 MW hybrid in Laurens, GA · In queue since May 2023 · Proposed COD October 2026
200 MW
Capacity
1
Components
Solar
3 years
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-05
The Live Oak Solar project is a proposed 200 MW hybrid solar and battery energy storage project located in Laurens County, Georgia. The project consists of 200 MW of solar generation. It is listed in the Georgia Transmission Corporation (GTC) interconnection queue as project GTC-GI-175.
The project entered the GTC queue on May 20, 2023, and has a proposed commercial operation date of October 5, 2026. Its interconnection status is currently in the System Impact Study phase. The point of interconnection is the 230 kV Bus at North Dublin 230 kV SS.
Generated from interconnection queue and public data sources
State
GA
County
Laurens
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
230 kV Bus at North Dublin 230 kV SS
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Live Oak Solar