TOCE GA 1 Solar
125 MW generation in Burke, GA · In queue since August 2023 · Proposed COD September 2026
125 MW
Capacity
1
Components
Solar
2y 9m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
The TOCE GA 1 Solar project is a proposed 125 MW solar generation facility in Burke County, Georgia. The project, under development by Georgia Transmission (GTC), entered the GTC interconnection queue as queue ID GTC-GI-177 on August 3, 2023. Its proposed commercial operation date is September 1, 2026. The project's interconnection status is currently in the System Impact Study phase.
The TOCE GA 1 Solar project has been featured in recent industry news, with four articles covering the development. The point of interconnection is the Greens Cut - Greens Cut Junction 115 kV Tap.
Generated from interconnection queue and public data sources
State
GA
County
Burke
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Greens Cut - Greens Cut Junction 115 kV Tap
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about TOCE GA 1 Solar