Pepper Hammock 200 MW
200 MW generation in Glynn, GA · In queue since August 2023 · Proposed COD August 2026
200 MW
Capacity
1
Components
Solar
2y 9m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-08-30
The proposed Pepper Hammock 200 MW project is a 200 MW solar generation facility located in Glynn County, Georgia. The project is listed in the Georgia Transmission (GTC) interconnection queue as queue ID GTC-GI-180, with an entry date of August 4, 2023. The proposed commercial operation date is August 30, 2026.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Thalmann - Offerman 230 kV transmission line. The developer is not specified in the queue data. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
GA
County
Glynn
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Thalmann - Offerman 230 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.