Hammond Solar
225 MW generation in Floyd, GA · In queue since September 2023 · Proposed COD November 2025
225 MW
Capacity
1
Components
Solar
2y 8m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
2y 2m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-30
Hammond Solar is a proposed 225 MW solar generation project located in Floyd County, Georgia. The project is being developed within the Georgia Transmission Corporation (GTC) service area. It entered the GTC interconnection queue (GTC-GI-181) on September 19, 2023, with a proposed commercial operation date of November 30, 2025. Its interconnection status is currently in the System Impact Study phase.
The proposed project consists of 225 MW of solar photovoltaic generation. Hammond Solar's point of interconnection (POI) is the Hammond - Anniston 230 kV transmission line. The project has been the subject of recent news coverage, with eight articles appearing in categories such as regulatory, industry, deals, and grid.
Generated from interconnection queue and public data sources
State
GA
County
Floyd
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Hammond - Anniston 230 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN