Pelham Solar
120 MW generation in Charlton, GA · In queue since September 2023 · Proposed COD November 2025
120 MW
Capacity
1
Components
Solar
2y 8m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
2y 2m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-30
The Pelham Solar project is a proposed 120 MW solar generation project located in Charlton County, Georgia. The project is being developed within the Georgia Transmission Corporation (GTC) service area. It entered the GTC interconnection queue (GTC-GI-182) on September 20, 2023, and has a proposed commercial operation date of November 30, 2025.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Folkston - St. George 115 kV transmission line. The Pelham Solar project has appeared in recent news coverage regarding solar development in the Southeast region.
Generated from interconnection queue and public data sources
State
GA
County
Charlton
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Folkston - St. George 115 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Pelham Solar