Beaver Creek Solar
183 MW hybrid in Baldwin, GA · In queue since September 2023 · Proposed COD April 2027
183 MW
Capacity
1
Components
Solar
2y 8m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-01
Beaver Creek Solar is a proposed 183 MW hybrid solar and battery energy storage project in Baldwin County, Georgia. The project, which consists of 183 MW of solar generation, is located in the Southeast region and is being developed within the Georgia Transmission (GTC) service area.
The project is listed in the GTC interconnection queue as entry GTC-GI-184, with a queue entry date of September 20, 2023. Its proposed commercial operation date is April 1, 2027, and its interconnection status is currently in the System Impact Study phase. Beaver Creek Solar has been the subject of recent news coverage related to regulatory matters.
Generated from interconnection queue and public data sources
State
GA
County
Baldwin
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Gordon - Milledgeville (White) 115 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Beaver Creek Solar