SR Bacon II Solar
115 MW generation in Bacon, GA · In queue since September 2023 · Proposed COD November 2027
115 MW
Capacity
1
Components
Solar
2y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-11-30
The SR Bacon II Solar project is a proposed solar generation facility with a total capacity of 115 MW. It is located in Bacon County, Georgia, within the Southeast region. The project is listed in the Georgia Transmission (GTC) interconnection queue under queue ID GTC-GI-185, with an interconnection queue entry date of September 28, 2023. The proposed commercial operation date is November 30, 2027, and the Interconnection Agreement (IA) has been executed.
The project is linked to the existing SR Bacon II operating plant (EIA ID 68553).
Generated from interconnection queue and public data sources
State
GA
County
Bacon
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Offerman - Douglas 230 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.