TOCE GA Solar 2
350 MW generation in Bartow, GA · In queue since January 2024 · Proposed COD July 2027
350 MW
Capacity
1
Components
Solar
2y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
TOCE GA Solar 2 is a proposed 350 MW solar generation project located in Bartow County, Georgia. The development project, under the entity GTC, is interconnected to the Georgia Transmission system. It entered the GTC interconnection queue as queue ID GTC-GI-188 on January 8, 2024, with a proposed commercial operation date of July 1, 2027.
The interconnection agreement for TOCE GA Solar 2 is currently listed as "In Progress (unknown study)". The point of interconnection is the Bowen _x0013_ Judy Mountain 230 kV line tap. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
GA
County
Bartow
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Bowen _x0013_ Judy Mountain 230 kV line tap
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.