TOCE GA Solar 4
100 MW generation in Jefferson, GA · In queue since January 2024 · Proposed COD June 2027
100 MW
Capacity
1
Components
Solar
2y 4m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
TOCE GA Solar 4 is a proposed 100 MW solar generation project in Jefferson County, Georgia. The project is being developed within the Georgia Transmission (GTC) interconnection queue, identified as GTC-GI-189. The queue entry date is January 8, 2024, with a proposed commercial operation date of June 1, 2027. Its interconnection status is currently in the System Impact Study phase.
The project, which appeared in recent industry news, consists of 100 MW of solar photovoltaic generation. The point of interconnection (POI) is the Wadley _x0013_ Waynesboro TL line tap.
Generated from interconnection queue and public data sources
State
GA
County
Jefferson
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Wadley _x0013_ Waynesboro TL line tap
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about TOCE GA Solar 4