Spain Energy Center
141 MW hybrid in Brooks, GA · In queue since January 2024 · Proposed COD December 2028
141 MW
Capacity
1
Components
Solar
2y 4m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-13
The Spain Energy Center is a proposed 141 MW hybrid solar and battery energy storage project located in Brooks County, Georgia. The project, which consists of 141 MW of solar capacity, is being developed within the Georgia Transmission Corporation (GTC) service area.
The project is listed in the GTC interconnection queue as project GTC-GI-190, with an interconnection queue entry date of January 9, 2024. Its proposed commercial operation date is December 13, 2028, and its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Spain 230 kV Substation. The Spain Energy Center has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
GA
County
Brooks
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Spain 230 kV Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Spain Energy Center