Smarr CC
2,000 MW generation in Monroe, GA · In queue since August 2024 · Proposed COD March 2028
2,000 MW
Capacity
1
Components
Gas
1y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-31
The Smarr CC project is a proposed 2000 MW gas-fired generation project located in Monroe County, Georgia. The project is being developed within the Georgia Transmission Corporation (GTC) service area. It is listed in the GTC interconnection queue as project GTC-GI-193, with an interconnection queue entry date of August 5, 2024.
The proposed commercial operation date for the Smarr CC project is March 31, 2028. The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is planned for the Big Smarr 500 kV substation.
Generated from interconnection queue and public data sources
State
GA
County
Monroe
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Big Smarr 500 kV substation (TBD)
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Smarr CC