SR Grady (GTC-GI-196) — Project Summary

Queue ID
GTC-GI-196
Capacity
150 MW
Technology
Solar
Status
active
Location
Grady, GA
Region
Southeast
Developer
IA Status
System Impact Study

SR Grady

GTC-GI-196BetaActiveSolarGTCLBNL

150 MW generation in Grady, GA · In queue since August 2024 · Proposed COD December 2028

150 MW

Capacity

1

Components

Solar

1y 9m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection

Total Duration

4y 4m

Impact Study25%
Queue EntryAug 31, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-15

About

The SR Grady project is a proposed 150 MW solar generation project located in Grady County, Georgia. Interconnection is requested through the Georgia Transmission (GTC) queue, identified as GTC-GI-196, with a queue entry date of August 31, 2024. The proposed commercial operation date is December 15, 2028. The project's interconnection status is currently in the System Impact Study phase.

The point of interconnection (POI) is the South Bainbridge _x0013_ Thomasville 230 kV TL. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

GA

County

Grady

Grid Region

Southeast

Market

Developer

Utility

Georgia Transmission

Entity

GTC

Service Type

Point of Interconnection

South Bainbridge _x0013_ Thomasville 230 kV TL

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Southern Company
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about SR Grady