Rebecca Solar
120 MW generation in Turner, GA · In queue since December 2024 · Proposed COD December 2028
120 MW
Capacity
1
Components
Solar
1y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The Rebecca Solar project is a proposed 120 MW solar generation facility in Turner County, Georgia. The project is being developed within the Georgia Transmission (GTC) interconnection queue, identified as GTC-GI-199, with a queue entry date of December 11, 2024. The proposed commercial operation date is December 1, 2028.
The interconnection agreement (IA) for Rebecca Solar is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the North Tifton - Pitts 230 kV line. The project has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
State
GA
County
Turner
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
North Tifton - Pitts 230 kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Rebecca Solar