Scarboro Solar
125 MW hybrid in Miller, GA · In queue since December 2024 · Proposed COD February 2031
125 MW
Capacity
1
Components
Solar
1y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2031
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-02-28
The Scarboro Solar project is a proposed 125 MW hybrid solar and battery energy storage development in Miller County, Georgia. The project, located in the Southeast region, consists of 125 MW of solar capacity. Scarboro Solar is interconnected with Georgia Transmission (GTC) and entered the GTC interconnection queue as project GTC-GI-200 on December 17, 2024.
The proposed commercial operation date (COD) for Scarboro Solar is February 28, 2031. The project's interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The point of interconnection (POI) for the project is the Grove Church 115 kV Substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
GA
County
Miller
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Grove Church 115 kV Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Scarboro Solar