57 MW generation in Peach, GA · In queue since December 2024 · Proposed COD December 2029
57 MW
Capacity
1
Components
Solar
1y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
5 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
The SR Peach project is a proposed 57 MW solar generation facility in Peach County, Georgia. The project is being developed within the Georgia Transmission (GTC) service area. It is listed in the GTC interconnection queue as project GTC-GI-201, with an entry date of December 17, 2024. The proposed commercial operation date is December 31, 2029.
The interconnection agreement for the SR Peach project is currently listed as "In Progress (unknown study)". The point of interconnection is the Ft. Valley #1 - Ft. Valley #2 115 kV line. The project has appeared in recent news coverage regarding solar development in the Southeast.
Generated from interconnection queue and public data sources
State
GA
County
Peach
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Ft. Valley #1 - Ft. Valley #2 115 kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.