SR Jefferson
200 MW generation in Jefferson, GA · In queue since December 2024 · Proposed COD December 2029
200 MW
Capacity
1
Components
Solar
1y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
5 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
The SR Jefferson project is a proposed 200 MW solar generation project located in Jefferson County, Georgia. The project is listed in the Georgia Transmission Corporation (GTC) interconnection queue as queue ID GTC-GI-204, with an entry date of December 18, 2024. The proposed commercial operation date is December 31, 2029. The interconnection agreement status is listed as "In Progress (unknown study)".
The SR Jefferson project has been the subject of recent news coverage, with two articles categorized as regulatory and deals. The point of interconnection is Sandersville #1 - Wadley 115 kV via Pervis.
Generated from interconnection queue and public data sources
State
GA
County
Jefferson
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Sandersville #1 - Wadley 115 kV via Pervis
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26