SR Wrens
194 MW generation in Jefferson, GA · In queue since December 2024 · Proposed COD December 2029
194 MW
Capacity
1
Components
Solar
1y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
5 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
The SR Wrens project is a proposed 194 MW solar generation facility located in Jefferson County, Georgia. The project is being developed within the Georgia Transmission (GTC) service area in the Southeast region. It entered the GTC interconnection queue as project GTC-GI-205 on December 19, 2024, with a proposed commercial operation date of December 31, 2029.
The interconnection agreement (IA) for the SR Wrens project is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Wrens - Hobnail 230 kV Line. The project has appeared in recent news coverage regarding renewable energy development in Georgia.
Generated from interconnection queue and public data sources
State
GA
County
Jefferson
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Wrens - Hobnail 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.