IID-GI-2020-142A
30 MW hybrid in Imperial, CA · In queue since November 2020 · Proposed COD February 2026
30 MW
Capacity
1
Components
Solar
5y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
5y 3m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-02-01
The proposed project IID-GI-2020-142A is a 30 MW hybrid Solar+Battery development project located in Imperial County, California. The project consists of 30 MW of solar generation capacity. It is interconnected within the Imperial Irrigation District (IID) queue, having entered the queue on November 16, 2020. The proposed commercial operation date is February 1, 2026.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the 92kV R line. The project is currently listed as active within the IID interconnection queue.
Generated from interconnection queue and public data sources
State
CA
County
Imperial
Grid Region
Mountain West
Market
—
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Service Type
—
Point of Interconnection
92kV R line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project IID-GI-2020-142A