IID-GI-2021-147
75 MW hybrid in Imperial, CA · In queue since November 2021 · Proposed COD April 2024
75 MW
Capacity
1
Components
Solar
4y 6m
In Queue
System Impact Study
IA Status
COD target: 2024
Total Duration
2y 5m
Schedule
25 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-04-01
IID-GI-2021-147 is a proposed 75 MW hybrid solar and battery project located in Imperial County, California. The project consists of 75 MW of solar generation capacity. It is listed in the Imperial Irrigation District (IID) interconnection queue, with an entry date of November 17, 2021. The proposed commercial operation date is April 1, 2024.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the 161kV N line. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
CA
County
Imperial
Grid Region
Mountain West
Market
—
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Service Type
—
Point of Interconnection
161kV N line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project IID-GI-2021-147