IID-GI-2021-148
90 MW hybrid in Imperial, CA · In queue since November 2021 · Proposed COD October 2027
90 MW
Capacity
1
Components
Solar
4y 6m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
5y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-01
The proposed project IID-GI-2021-148 is a 90 MW solar and battery hybrid development project located in Imperial County, California. Interconnecting to the Imperial Irrigation District (IID) at the 92kV Anza Substation, the project consists of 90 MW of solar generation.
The project is currently active in the IID interconnection queue, having entered the queue on November 17, 2021. Its interconnection status is currently in the System Impact Study phase, with a proposed commercial operation date of October 1, 2027.
Generated from interconnection queue and public data sources
State
CA
County
Imperial
Grid Region
Mountain West
Market
—
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Service Type
—
Point of Interconnection
92kV Anza Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project IID-GI-2021-148