IID-GI-2021-151
77 MW generation in Imperial, CA · In queue since December 2021 · Proposed COD February 2028
77 MW
Capacity
1
Components
Geothermal
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-02-01
IID-GI-2021-151 is a proposed 77 MW geothermal generation project located in Imperial County, California. The project is listed in the Imperial Irrigation District (IID) interconnection queue with a queue entry date of December 30, 2021. Its proposed commercial operation date is February 1, 2028. The interconnection agreement status is listed as "In Progress (unknown study)".
The development project consists of a single 77 MW geothermal component. The point of interconnection is listed as "Proposed New Facility". The project is currently listed as "active" in the IID interconnection queue.
Generated from interconnection queue and public data sources
State
CA
County
Imperial
Grid Region
Mountain West
Market
—
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Service Type
—
Point of Interconnection
Proposed New Facility
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project IID-GI-2021-151