IID-GI-2022-160
50 MW hybrid in Imperial, CA · In queue since September 2022 · Proposed COD December 2024
50 MW
Capacity
1
Components
Solar
3y 8m
In Queue
System Impact Study
IA Status
COD target: 2024
Total Duration
2y 3m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
IID-GI-2022-160 is a proposed 50 MW hybrid solar and battery project located in Imperial County, California. The project consists of 50 MW of solar generation. It is in the Imperial Irrigation District (IID) interconnection queue, with an entry date of September 6, 2022. The proposed commercial operation date is December 1, 2024.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the 92kV K Line. The project has appeared in recent news coverage regarding energy development in the region.
Generated from interconnection queue and public data sources
State
CA
County
Imperial
Grid Region
Mountain West
Market
—
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Service Type
—
Point of Interconnection
92kV K Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.