IID-GI-2022-162
270 MW hybrid in Imperial, CA · In queue since September 2022 · Proposed COD June 2026
270 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
IID-GI-2022-162 is a proposed hybrid Solar+Battery project with a total capacity of 270 MW. The development is located in Imperial County, California, within the Imperial Irrigation District (IID) service area. The project, which consists of 270 MW of solar generation, entered the IID interconnection queue on September 8, 2022, with a proposed commercial operation date of June 1, 2026.
The interconnection agreement (IA) status for IID-GI-2022-162 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is designated as "Proposed New Facility". The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
CA
County
Imperial
Grid Region
Mountain West
Market
—
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Service Type
—
Point of Interconnection
Proposed New Facility
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project IID-GI-2022-162