IID-GI-2022-164
800 MW hybrid in Imperial, CA · In queue since November 2022 · Proposed COD March 2026
800 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 4m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-01
IID-GI-2022-164 is a proposed 800 MW hybrid solar and battery project located in Imperial County, California. The development project, which consists of 800 MW of solar power, is in the Imperial Irrigation District (IID) interconnection queue, with an entry date of November 30, 2022. The proposed commercial operation date is March 1, 2026, and the interconnection agreement status is listed as "In Progress (unknown study)".
The project has been the subject of recent news coverage, with 132 articles categorized as regulatory, deals, industry, grid, and development.
Generated from interconnection queue and public data sources
State
CA
County
Imperial
Grid Region
Mountain West
Market
—
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Service Type
—
Point of Interconnection
Proposed New Facility
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-31