IID-GI-2023-171
100 MW hybrid in Imperial, CA · In queue since April 2023 · Proposed COD December 2026
100 MW
Capacity
1
Components
Solar
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
IID-GI-2023-171 is a proposed 100 MW hybrid solar and battery project located in Imperial County, California. The project, consisting of 100 MW of solar generation, is in the Imperial Irrigation District (IID) interconnection queue, with an entry date of April 27, 2023. The proposed commercial operation date is December 1, 2026.
The interconnection agreement (IA) status for IID-GI-2023-171 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the 92kV C substation. The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
CA
County
Imperial
Grid Region
Mountain West
Market
—
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Service Type
—
Point of Interconnection
92kV C
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.