IID-GI-2023-175
150 MW hybrid in Imperial, CA · In queue since April 2023 · Proposed COD June 2028
150 MW
Capacity
1
Components
Solar
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
The proposed IID-GI-2023-175 project is a 150 MW hybrid solar and battery energy storage development in Imperial County, California. The project, located in the West region, is being proposed within the Imperial Irrigation District (IID) interconnection queue, with a queue entry date of April 28, 2023. The proposed commercial operation date is June 1, 2028.
The interconnection agreement (IA) status for the project is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the 230kV Sinclair Substation. Recent news coverage indicates interest in the project's progress.
Generated from interconnection queue and public data sources
State
CA
County
Imperial
Grid Region
Mountain West
Market
—
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Service Type
—
Point of Interconnection
230kV Sinclair Sub
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project IID-GI-2023-175