IP-546
3 MW generation in Baker, OR · In queue since December 2018 · Proposed COD December 2019
3 MW
Capacity
1
Components
Solar
7y 5m
In Queue
IA Executed
IA Status
Signed Aug 2021
Queue → IA
2y 8m
Total Duration
2y 8m
Schedule
78 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2019-12-01
The IP-546 development project is a proposed 3 MW solar generation facility in Baker County, Oregon. Developed by Durkee Solar, LLC, the project is interconnected with Idaho Power Company via the DRKE 12.47kV Feeder.
The project is listed in the IP (Idaho Power) interconnection queue with an entry date of December 18, 2018, and a proposed commercial operation date of December 1, 2019. The interconnection agreement (IA) was executed on August 26, 2021, and the project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
OR
County
Baker
Grid Region
Mountain West
Market
—
Developer
Durkee Solar, LLC
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
DRKE 12.47kV Feeder
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project IP-546