IP-562
42 MW hybrid in Malheur, OR · In queue since August 2019 · Proposed COD June 2022
42 MW
Capacity
1
Components
Solar
6y 9m
In Queue
IA Executed
IA Status
Signed Aug 2021
Queue → IA
2 years
IA → COD
10 months
Total Duration
2 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–30 months
Proposed COD: 2022-06-01
IP-562 is a proposed 42 MW hybrid solar and battery project located in Malheur County, Oregon. The project, developed by Moores Hollow PV1, LLC, consists of 42 MW of solar capacity. It is interconnected to the Idaho Power Company (IP) grid at the ONTO_x0013_WEJN 138kV Line point of interconnection.
The project entered the IP interconnection queue on August 5, 2019, with a proposed commercial operation date of June 1, 2022. The interconnection agreement (IA) was executed on August 31, 2021, though the project's current status is listed as suspended.
Generated from interconnection queue and public data sources
State
OR
County
Malheur
Grid Region
Mountain West
Market
—
Developer
Moores Hollow PV1, LLC
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
ONTO_x0013_WEJN 138kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project IP-562