IP-570
1,050 MW hybrid in Jerome, ID · In queue since October 2019 · Proposed COD December 2023
1,050 MW
Capacity
1
Components
Wind
6y 7m
In Queue
IA Executed
IA Status
Signed Mar 2022
Queue → IA
2y 5m
IA → COD
1y 9m
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 24–36 months
Proposed COD: 2023-12-01
The proposed IP-570 project is a 1050 MW hybrid wind and battery energy storage development in Jerome County, Idaho. The project, being developed by Magic Valley Energy, LLC, consists of 1050 MW of wind generation capacity. Interconnection to the Idaho Power Company system is planned at the MPSN 500kV point of interconnection.
The project entered the IP interconnection queue on October 17, 2019, with a proposed commercial operation date of December 1, 2023. An Interconnection Agreement was executed on March 23, 2022, though the project's current status is listed as suspended. The project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
ID
County
Jerome
Grid Region
Mountain West
Market
—
Developer
Magic Valley Energy, LLC
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
MPSN 500kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26