IP-605
240 MW hybrid in Elmore, ID · In queue since May 2021 · Proposed COD December 2024
240 MW
Capacity
1
Components
Solar
5 years
In Queue
IA Executed
IA Status
Signed Apr 2023
Queue → IA
1y 11m
IA → COD
1y 8m
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–30 months
Proposed COD: 2024-12-01
IP-605 is a proposed 240 MW solar and battery hybrid project located in Elmore County, Idaho. The development project, listed in the Idaho Power (IP) interconnection queue, is being developed by South Bennett Solar LLC. The project consists of 240 MW of solar capacity and an unspecified amount of battery storage.
The project entered the IP interconnection queue on May 27, 2021, with a proposed commercial operation date of December 1, 2024. The interconnection agreement (IA) for the project was executed on April 20, 2023. The point of interconnection is the RTSN 230kV Substation. The project's current status is listed as suspended.
Generated from interconnection queue and public data sources
State
ID
County
Elmore
Grid Region
Mountain West
Market
—
Developer
South Bennett Solar LLC
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
RTSN 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.