IP-609
200 MW hybrid in Sweetwater, WY · In queue since June 2021 · Proposed COD December 2025
200 MW
Capacity
1
Components
Solar
4y 11m
In Queue
IA Executed
IA Status
Signed May 2023
Queue → IA
1y 11m
IA → COD
2y 7m
Total Duration
1y 11m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-12-01
IP-609 is a proposed 200 MW hybrid solar and battery energy storage project located in Sweetwater County, Wyoming. The project, developed by NextEra Energy Resources Interconnection Holdings, LLC, is interconnected to Idaho Power Company via the JBRG 345kV Substation. It consists of 200 MW of solar capacity.
The project is listed in the IP interconnection queue with an entry date of June 28, 2021, and a proposed commercial operation date of December 1, 2025. The Interconnection Agreement (IA) was executed on May 9, 2023. The project is currently listed as active.
Generated from interconnection queue and public data sources
State
WY
County
Sweetwater
Grid Region
Mountain West
Market
—
Developer
NextEra Energy Resources Interconnection Holdings, LLC
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
JBRG 345kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.