132 MW hybrid in Twin Falls, ID · In queue since August 2021 · Proposed COD December 2025
132 MW
Capacity
1
Components
Wind
4y 9m
In Queue
IA Executed
IA Status
Signed Sep 2023
Queue → IA
2y 1m
IA → COD
2y 3m
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 24–36 months
Proposed COD: 2025-12-01
The IP-614 development project is a proposed 132 MW wind and battery hybrid project located in Twin Falls County, Idaho. The project, developed by Magic Valley Energy, LLC, is interconnected with Idaho Power Company and has a Point of Interconnection at the Rogerson 345kV Substation.
The project is listed in the IP interconnection queue with an entry date of August 6, 2021, and a proposed commercial operation date of December 1, 2025. The Interconnection Agreement (IA) for the project was executed on September 22, 2023, though the project's current status is listed as suspended. The project consists of 132 MW of wind generation capacity.
Generated from interconnection queue and public data sources
State
ID
County
Twin Falls
Grid Region
Mountain West
Market
—
Developer
Magic Valley Energy, LLC
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
Rogerson 345kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.